On Friday 28th of May, the field site in Cornwall have now completed the drilling of a second well: UD-2 reached a depth of 2393m, having reached the Porthtowan Fault Zone. UD-1 reached a depth of 5275m in April Demobilisation of the Innovarig will now commence from this week. They are currently in the process of removing all the ancillary equipment before the removal of the main rig elements by the end of July. Once the rig and ancillary equipment have all been removed from site, the team will need to take time to prepare for the testing phase of the project. This may include the need for a ‘workover’ rig to carry out some activities.